SolarStock USA
SolarStock USA
U.S. Solar Inventory

Market Note · Tax credits · Domestic content

Domestic content: the bar rises to 55% in 2027

From January 1, 2027, a solar project that starts construction needs 55% U.S.-made content, by cost, to earn the domestic content bonus on the 45Y and 48E credits. Here is how the test works and where the module sits in it.

What the statute says

The domestic content bonus raises the clean electricity credits for projects built with U.S. steel, iron and manufactured products. Under Section 45Y(g)(11), the production credit "shall be increased by an amount equal to 10 percent." The investment credit borrows the rules of Section 48(a)(12): a 10 percentage-point increase for a project meeting the Section 48(a)(9)(B) requirements (prevailing wage and apprenticeship, or a project under 1 MW AC), 2 points otherwise.

Two tests must both be met:

  • Steel and iron: steel and iron that are components of the facility must be "produced in the United States," applied "in a manner consistent with section 661.5 of title 49, Code of Federal Regulations."
  • Manufactured products: at least the "adjusted percentage" of "the total costs of all such manufactured products" must come from products "mined, produced, or manufactured in the United States."

The threshold steps up on January 1

The adjusted percentage depends on when construction begins. Section 45Y(g)(11)(C) sets 45% for construction beginning in 2025, 50% in 2026 and 55% "in the case of a facility the construction of which begins after December 31, 2026."

For the investment credit, section 70513(d) of Public Law 119-21 rewrote Section 48E(a)(3)(B): 40% for construction beginning before June 16, 2025; 45% from June 16, 2025 through 2025; 50% "during calendar year 2026"; and 55% for construction that "begins after December 31, 2026." Section 70513(g)(2) applies that change "on or after June 16, 2025."

Where the module sits in the cost test

Most projects measure the percentage with the elective safe harbor in Notice 2025-08, effective January 16, 2025, which assigns each component a fixed share of total manufactured-product cost instead of using the manufacturer's actual costs. For a ground-mount tracking project the table assigns:

  • Cells: 38.0%, the largest single line.
  • Other module components (frame/backrail, front glass, encapsulant, backsheet, junction box, edge seals, pottants, bus ribbons, bypass diodes): 23.1% combined (our arithmetic from the table).
  • Module "Production": 4.7%, which counts only "if all of the Manufactured Product Components of that Manufactured Product APC are domestically produced."
  • Tracker: torque tube 11.0%, plus drive, actuator, rails and other parts.

For a ground-mount fixed-tilt project there is no tracker line, so the module carries more weight: cells alone are 53.2%. A separate column applies when modules use U.S. cells made exclusively from U.S. wafers; for a tracking project the notice puts module components at 69.7% and module production at 3.7% under that column.

What this means for module buyers

  • Start date sets the bar. A project starting construction in 2026 works to 50%; one starting in 2027 works to 55%. Ask which year the project's tax counsel assigns before fixing the bill of materials.
  • Cells drive the result. A module assembled in the U.S. with imported cells can contribute at most its non-cell components, and its production share only if every component is domestic. On the tracking table that leaves far less than the module's 65.8% total (our arithmetic). Ask the module maker for a component-level origin statement, not just a country of assembly.
  • 2027 solar starts face two deadlines. Projects that begin construction in 2027 must also be placed in service by December 31, 2027 to keep the credit; see our placed-in-service note.
  • Domestic content is not FEOC. The material-assistance rules are a separate test; see FEOC: MACR safe-harbor tables. For the component split, see the Domestic Content Playbook 2026.

This note summarizes official text and is not tax advice; confirm a project's domestic content position with a tax adviser.

In SolarStock USA warehouses now · live

IRA 45X domestic modules (Georgia line): 0.06 MW ready to ship (3 pallets).

Sources
  1. 26 U.S.C. 45Y(g)(11) — domestic content bonus credit amount and adjusted percentage — U.S. Code (via GovInfo)
  2. 26 U.S.C. 48(a)(12) — domestic content bonus rules applied to 48E — U.S. Code (via GovInfo)
  3. Public Law 119-21 (OBBBA), section 70513(d) and (g)(2) — 48E domestic content percentages — U.S. Congress (via GovInfo)
  4. Notice 2025-08 — First Updated Elective Safe Harbor for the domestic content bonus — IRS / U.S. Treasury

Market Notes are prepared by SolarStock USA for procurement professionals. They summarize public documents and do not constitute legal, tax or investment advice.