Market Note · Tax credits · 48E/45Y
48E/45Y: new solar must be in service by end-2027
The July 4, 2026 beginning-of-construction deadline has passed. For a solar project that starts construction now, the clean electricity credits (Sections 45Y and 48E) only apply if it is placed in service by December 31, 2027 — and that date drives module procurement.
What the statute says
Section 70513(a) of the 2025 budget law, Public Law 119-21 (OBBBA), added Section 48E(e)(4): the investment credit "shall not apply to any qualified property placed in service by the taxpayer after December 31, 2027, which is part of an applicable facility" — a facility that "uses wind" or "uses solar energy to produce electricity." Section 70512 does the same for the 45Y production credit. Section 48E(e)(4)(C) excepts energy storage placed in service at such a facility.
The cutoff does not reach every project. Under Section 70513(g)(5), it applies "to facilities the construction of which begins after the date which is 12 months after the date of enactment." Notice 2025-42 puts that date at July 4, 2026: a taxpayer avoids the 2027 cutoff only by showing that construction began "before July 5, 2026."
How the IRS tests "beginning of construction"
Notice 2025-42 makes the Physical Work Test the sole method for that deadline, except for small solar (below). Key points from the text:
- Construction begins "when physical work of a significant nature begins." The test "focuses on the nature of the work performed, not the amount or the cost."
- For solar, on-site work "may include the installation of racks or other structures to affix photovoltaic (PV) panels." Off-site work counts too — for example manufacture of racks, rails, inverters or transformers — under a binding written contract signed before the work starts.
- Planning, financing, permits, studies, site clearing and test drilling are "preliminary activities" and do not count.
- Inventory does not count. Work on a component "that is either in existing inventory or is normally held in inventory" by the seller is excluded.
- The Five Percent Safe Harbor survives only for a "low output solar facility" of no more than 1.5 MW (AC). For a DC system, output is the lesser of the summed DC nameplate or the nameplate of the first inverting component.
Projects that did begin construction in time must still keep a "continuous program of construction." Under the notice's Continuity Safe Harbor, placing the facility in service within four calendar years after the year construction began satisfies it — the notice's own example is a start on August 20, 2025 and in service by December 31, 2029. The notice applies to facilities whose construction did not begin before September 2, 2025.
What this means for module buyers
- Two project populations. Projects that began construction by July 4, 2026 work to their continuity window. Projects starting now work to a hard December 31, 2027 placed-in-service date. Ask which group a project sits in before setting the delivery schedule.
- Buying modules is not starting construction. Modules a distributor normally holds in inventory fall under the notice's inventory exclusion, so a purchase order by itself does not establish a start date. That is a question for the project's tax counsel, not the module invoice.
- Bought-in "safe-harbored" equipment needs care. The notice says that when tangible property is transferred to an unrelated party, work done by the seller "will not be taken into account" for the buyer's Physical Work Test.
- Lead time is now a credit risk. For 2027 projects, a late container can push the in-service date past December 31, 2027. Modules already landed in the U.S. remove customs and transit risk from that schedule; AD/CVD cash deposits are covered in our Solar IV cash-deposit note.
- FEOC still applies. Construction beginning after December 31, 2025 is also subject to the material-assistance rules — see FEOC: MACR safe-harbor tables and our FEOC page.
This note summarizes official text and is not tax advice; confirm a project's start date and credit position with a tax adviser.
All landed modules: 109.14 MW ready to ship (5,920 pallets).
- Sunpro Power SPDG440-N108M10 — 18.04 MW
- Waaree BiN-08-585-30HS — 11.06 MW
- Waaree BiN-08-570-35HS — 7.93 MW
- CW Energy CWT595-144TNB10 — 7.69 MW
- CW Energy CWT620-132TNB12R — 7.63 MW
- ZN Shine ZXM7-UHLDD144-590W — 6.67 MW
- Public Law 119-21 (OBBBA), sections 70512 and 70513 — termination of 45Y/48E for wind and solar facilities — U.S. Congress (via GovInfo)
- Notice 2025-42 — Beginning of construction requirements for applicable wind and solar facilities — IRS / U.S. Treasury
Market Notes are prepared by SolarStock USA for procurement professionals. They summarize public documents and do not constitute legal, tax or investment advice.